Project Overview
- Underground Mine;
- Board and pillar operation;
- Drift access located at thinnest point of basalt cover and lowest depth of cover;
- Mine plan design to maximise resource recovery; and
- Pillars designed to minimise surface.
Mine schedule
- Target commencement of mining by 2014;
- Production of 1Mtpa over a 15-year mine life; and
Resource potential:
- Yield between 50% and 65%, due to un-mined pillars as part of the mine design.
- Total JORC resource of 20.6Mt, 3.4Mt Measured, 10.8Mt Indicated and Inferred category of 6.4Mt